I definitely will try to slow the slab curing down, thanks for the advice.
Lots of progress these past couple of days. The excavator finished up the grading and built the new driveway.
The electrician came and installed a junction box and buried cable.
The mesh was placed for the slab
My trusty radiant heat expert came by and we installed a whole bunch of pex. Many thanks Mrdouglas!
Here is the pex all installed, love that orange!.
The pex went so well that we actually got to install the sill plates as well- no pics yet. all and all I am beginning to see the light at the end of the tunnel which puts the building into my hands. I have the slab to wait for, but then I am responsible for the pace and construction.
Pete